1, the extruder out of the box acceptance, the equipment out of the box acceptance, is the extruder into the factory acceptance of the first step. Unpacking acceptance, it is likely to find that there are parts damaged and the number of parts does not match the packing list. Therefore, the acceptance of equipment out of the box, should supply, transportation, equipment, power and equipment management personnel to participate in the joint acceptance of the case, found
Promptly contact the supplier for negotiation. Equipment out of the box acceptance of the work order is as follows.
① Before opening the box to check whether there is damage to the equipment box and found the box damaged, take a picture for the record.
② clear the box of dust, dirt and dirt.
③ open the box cover to see if there is any damage to the parts, verify the device name, model specifications and order the contract is consistent. Remove the side panel without any problem. Find packing list, certificate and equipment manual.
④ According to the packing list and equipment manual inventory of equipment and ancillary components, at the same time to inventory registration.
⑤ Check the appearance of the equipment rust and paint missing site.
⑥ with gasoline cleaning equipment, ancillary parts and barrel and screw, after cleaning coated with a layer of lubricant storage, ready to test.
2, the location of the extruder line Choose the extruder production line location arrangements, from the convenience of production considerations, as far as possible from the finished product library and raw materials for production more recent; from the safety point of view, away from the boiler room and substation. In the workshop location, to make the operator easy to operate, good lighting, extruder control box on the operator’s right hand side.
3, the basis of the extruder and installation of equipment, in addition to be able to withstand the weight of the equipment itself and the production of raw materials, but also to withstand the dynamic load when the extruder work. Extruder working speed is not high, dynamic load is small, so no special foundation requirements. According to the basic operating instructions. With 300 or 400 cement, sand and stones washed with water, pay attention to the mixing ratio of the three, because the concrete has a greater impact on the basis of quality. In the second irrigation anchor bolt hole, with cement than the first water cement with a higher grade